Atomic Energy History · Feature

No Great Harm: How the General Design Criteria Locked In a Light-Water Fleet

Engraving-style illustration of a cuckoo chick in a songbird’s nest, tagged ‘GDC,’ with a speckled egg labeled ‘PDC’ pushed out over the rim. Caption: Fig. 1. The Cuckoo in the Nest.
The common cuckoo lays its egg in another bird’s nest. When the chick hatches, it pushes out the host’s own eggs.

There is a missing definition in 10 CFR Part 50. It has been missing for over 50 years…

That missing definition is for “principal design criteria” (PDC), which 10 CFR 50.34 requires be included in an application for a construction permit of nuclear reactors. The application must then relate the design bases to the PDC.

In the nuclear regulations, you would expect to find definitions of critical terms rich in specific technical meaning, such as design bases (even if they have led to decades of confusion). Given that the PDC are an integral part of securing a construction permit, the missing definition is a highly uncharacteristic curiosity to find in a set of definitions that devotes space to defining even mundane terms such as “Act,” “atomic weapon,” “Commission,” and “common defense and security.”

Appendix A, the General Design Criteria, provides a description of what the principal design criteria are, but a description is not a definition: “The principal design criteria establish the necessary design, fabrication, construction, testing, and performance requirements for structures, systems, and components important to safety…”

Between 1965 and 1971, only one document that I’ve found actually contains a definition of “principal design criteria”: the 1966 SAR guide for the organizing and contents of safety analysis reports. The definition provided was this:

Principal Design Criteria means those fundamental architectural and engineering design objectives established for the project. As such, these criteria represent the broad frame of reference within which the more detailed plant design effort is to proceed and against which the end project will be judged.

This definition, read within the context of the full guide, explained what kinds of things matter (design objectives for a particular project), who establishes them (the applicant), and their role (a standard that sits above the design bases).

But this definition was never codified. It was never included in a draft rule published in the Federal Register. The 1966 proposed rule pointed applicants to the SAR guide and adopted a version of its design bases definition, but not its definition of principal design criteria.

By the time the GDC had been settled after nearly five years of development, the definition was no longer accurate, and for light-water reactors, the GDC had become a universal standard that would soon displace the PDC.

In 1966, the AEC defined the principal design criteria by what they were: the applicant’s own design objectives for the project. By 1971, it described them by what they do: establish requirements for SSCs important to safety. A definition excludes; a description admits. The General Design Criteria fit the description, so they could take the PDC’s place.

This article is about how the General Design Criteria displaced the principal design criteria and entrenched a light-water-reactor-only fleet.

Overload Drove the Need for a New Approach

For water-cooled reactors, the principal design criteria are a relic of a licensing philosophy that began with one set of intentions and morphed into something else.

Design criteria were required to be included in applications from the beginning.

The original regulations issued in 1956, agnostic to reactor type, required the hazards summary report (later renamed safety analysis report) to be submitted with the application. The AEC would indicate which parts of that became the technical specifications that became part of the license for a construction permit. A description of the facility had to be included, and it was to be “based on the design criteria for the facility as a whole and for those major component parts which are essential to the safe operation of the facility.”

The applicant supplied the design criteria, and the AEC evaluated them. The process involved a unique review for each application on a case-by-case basis, along with required public licensing board hearings.

By the early 1960’s, commercial nuclear power was a rapidly expanding industry. The AEC established the Power Demonstration Reactor Program in 1955. Then Shippingport (50 MWe) went critical in 1957. Dresden 1 (180 MWe, GE BWR) was completed in 1959. Westinghouse completed Yankee Rowe (140 MWe, PWR) by 1960 and sold two other larger PWRs in 1962. In 1963, Oyster Creek (515 MWe, BWR) was ordered and was intended by GE to be a turnkey contract to make inroads into the market.

According to Walker in Containing the Atom (1992), the AEC issued 38 construction permits between 1963 and 1969, and power ratings rapidly expanded from 500-1000 MWe even while operating experience remained limited to plants of 200 MWe and smaller in size.

The rapid growth of the industry quickly overwhelmed the AEC’s regulatory division as the volume of application requests poured in. They realized they needed a better approach to licensing reviews, and the industry sought certainty and speed.

The flood of applications and the generally disorganized documentation of submittals made the need for standardization obvious to the AEC staff and industry alike.

Short Chronological History of GDC Versions

Up to this point, each review was essentially unique and contained multiple layers of scrutiny. “The complexity and redundancy that characterized the licensing process by 1964 were a source of concern to the nuclear industry” (Walker, Containing the Atom, Chapter 3). Walker quoted an observer as characterizing the applicant’s licensing journey as something guaranteed to contain “unpleasant surprises ahead of him.”

A regulatory review panel under the chairmanship of William Mitchell (“The Mitchell Panel”) convened by AEC Chairman Glenn Seaborg in January of 1965 presented a report in July of that year with its recommendations for “achieving substantial improvements in the regulatory process.”

The panel noted that it was taking about a year at minimum to move from an applicant’s initial submittal to receipt of a construction permit. They hoped to reduce that to six months so that nuclear remained competitive with fossil plants, and it also noted indefiniteness in the licensing process that created uncertainty.

One of its recommendations was to establish criteria “which are the minimum which must be met in order to be acceptable as a licensed facility.” It stated that these criteria should initially be focused on “those reactors which are being proposed for commercial installations in the greatest numbers.” At that time, this meant water-cooled PWRs and BWRs.

By 1965, to those ends, an effort had been underway by the AEC staff in conjunction with the Advisory Committee on Reactor Safeguards (ACRS) “to develop general criteria to assist in the evaluation of applications for nuclear power plant construction permits.”

Sharing the criteria with the industry would serve as a guide for developing their applications; share the rubric in advance, and ideally the submittals will match the scoring key.

Between November of 1965 and the final Appendix A of February 1971, there were four main versions of the General Design Criteria released:

VersionDateCountAEC’s labelSource
Draft criteria, press release H-252Nov 22, 196527“interim guidance”press release
Proposed Appendix AJuly 11, 196770“guidance” for PDC32 FR 10213
Staff revision to the ACRSJuly 15, 196954“minimum requirements”ML20044B578
Final Appendix AFeb 20, 197155“minimum requirements for the principal design criteria”36 FR 3255

The first version released for public comment appeared on November 22, 1965, attached to a press release.

How the Electrical GDC Changed Over Time

There were 27 criteria in the initial 1965 release. Over the next five years, the criteria increased in both magnitude (55 total criteria) and volume (requirement density per criterion).

Between the 27 criteria of the draft criteria and the 55 contained in the 1971 rule, the electrical criteria grew from a single sentence to the multiple paragraphs we have today in GDC 17 and 18.

The electrical requirements (Criterion 21) in the 1965 criteria contained broad principles and few specifics. There was no differentiation at all between onsite and offsite power systems:

Sufficient normal and emergency sources of electrical power must be provided to assure a capability for prompt shutdown and continued maintenance of the reactor facility in a safe condition under all credible circumstances.

In the 1967 proposal, the electrical criterion was bumped to item number 39 and was expanded to specifically mention for the first time the requirements of independence, redundancy, and an early form of the single failure criterion (applied then also to the offsite power system!):

Criterion 39–Emergency Power for Engineered Safety Features (Category A). Alternate power systems shall be provided and designed with adequate independency, redundancy, capacity, and testability to permit the functioning required of the engineered safety features. As a minimum, the onsite power system and the offsite power system shall each, independently, provide this capacity assuming a failure of a single active component in each power system.

The 1969 revision two years later took a form more closely resembling the final 1971 rule. The electrical criteria were expanded and split into two separate items, GDC 17 and 18.

The major changes between the 1969 revision and the 1971 rule were associated with clearly specifying and more fully defining requirements for two separate power systems, onsite and offsite. As documented in the Okrent Report, it was the result of negotiation and compromise between the ACRS (who demanded two separate lines), the staff majority (who argued one incoming line was enough based on reliability numbers), and the industry, who insisted on eliminating two separate rights of way. A tracked-changes version of GDC 17 between the 1969 revision and 1971 final rule are below:

Onsite An onsite electrical power system and an offsite electrical power systems system shall be provided with to permit functioning of structures, systems, and components important to safety. The safety function for each system (assuming the other system is not functioning) shall be to provide sufficient capacity and capability to assure that (1) specified acceptable fuel damage design limits and design conditions of the reactor coolant pressure boundary are not exceeded during as a result of anticipated operational occurrences and (2) the core is cooled and containment integrity and other vital functions are maintained following in the event of postulated accidents.

The system safety function for the onsite and offsite electrical power systems sources, including the batteries, and the onsite electrical distribution system, shall be that each provide have sufficient capacity to permit functioning of structures independence, systems redundancy, and components important testability to perform their safety functions assuming a single failure.

Offsite electrical Electrical power shall be provided from the transmission network to the site preferably switchyard shall be supplied by two physically independent transmission lines (not necessarily on separate rights of way) designed and located so as to suitably minimize the likelihood of their simultaneous failure under operating and postulated accident and environmental conditions. The Two physically independent circuits from the switchyard to the onsite electrical distribution system shall be provided. Each of these circuits shall be designed to be available in sufficient time following a loss of all onsite alternating current power sources and the onsite portions other offsite electrical power circuit, to assure that specified acceptable fuel design limits and design conditions of the offsite system reactor coolant pressure boundary are not exceeded. One of these circuits shall be designed with sufficient independency to be available within a few seconds following a loss-of-coolant accident to assure that core cooling, redundancy containment integrity, and testability to perform their other vital safety function assuming failure of a single active component functions are maintained.

Provisions shall be included to minimize the probability of losing offsite electrical power from any of the remaining sources as a result of, or coincident with, the loss of electrical power generated by the nuclear power unit, the loss of power from the transmission network, or the loss of power from the onsite electrical power sources.

From Guidance to Minimum Requirements

The AEC staff was split from the beginning on the nature of the GDC. At Meeting 223 on November 10, 1965, Commissioner Ramey thought it was unclear that the design criteria were established to provide guidance to applicants. In response, Mr. Doan explained that the “Regulatory staff viewed the proposed design criteria more as general requirements than as guidance, wherever they may be applicable.”

In February of 1967, Hanauer described the latest version as “still mostly harmless pious platitudes.”

“Considering how the staff has interpreted ‘fulfillment in principle’ of some of the July criteria by some applicants,” Hanauer didn’t think they’d offer a quantum leap in safety, nor reduce ACRS workload. On the other hand, he saw “no great harm in promulgating these criteria.”

The tension of whether the GDC would be guidance for developing the PDC or minimum requirements for nuclear power plants originated from inside the AEC.

To the Public, Initially, the GDC Were Guidance

A letter from Price to the Commission about two weeks before the 1965 criteria were issued characterized the GDC as reflecting “what has been past practice and express in general form various aspects of reactor facility design heretofore treated on a case by case basis.” The 1965 press release characterized them as “interim guidance.”

The principal design criteria were first introduced, without an accompanying definition, in the proposed rule issued in 1966. A footnote in those regulations directed the reader to the 1965 press release “for assistance in determining principal design criteria for the facility” that contained “General Design Criteria for Nuclear Power Plant Construction Permits.”

The 1967 proposal of the GDC published for comment in the Federal Register on July 11, 1967 reinforced their purpose as providing “guidance to applicants in developing the principal design criteria,” consistent with the footnote included in the 1966 proposed rules. Further, it stated that “These General Design Criteria would not add any new requirements, but are intended to describe more clearly present Commission requirements to assist applicants in preparing applications.”

The final 1968 regulation that updated the 50.59 rule preserved the appearance of “principal design criteria” (again without definition) in 50.34 from the proposed 1966 rule. Footnote 4 pointed the reader to the 1967 proposed Appendix A rule for “interim guidance in determining principal design criteria for nuclear reactors.”

After 1968, applicants were now required by 10 CFR 50.34 to submit principal design criteria with their license applications, documented in their preliminary and final safety analysis reports. The criteria were established by the applicant, and applicants were intended to refer to the proposed GDC for guidance in developing their own PDC.

But the Original Intent Was Requirements

The Mitchell panel of 1965 pushed a pursuit to establish “criteria and standards for the technical features of an installation which are the minimum which must be met in order to be acceptable as a licensed facility.”

Harold Price in a June 1965 meeting insisted standards existed “since reactors are judged and approved every day,” and that the Commission was “demanding a better definition of what these standards are.” The draft press release from November 3 called them “design and performance requirements…which have evolved over years” in licensing, while the final November 22 release characterized them as “criteria…which have evolved over years.”

During a subcommittee meeting on reactor design criteria in September of 1965, Mr. Rogers noted the intent of the GDC were to satisfy Harold Price’s desire for “a legalized regulatory process where licenses can be issued with little engineering judgment.” Guidance implies novel means can be supplied to meet general principles, requiring greater engineering judgment during a review for conformance; meeting minimum requirements diminishes the use of novelty.

The shape of the original intent was for the GDC rule to codify past practice as minimum requirements for a nuclear reactor application.

In Practice, a Flexible Yardstick 1965-1967

The years in which the draft criteria were circulating demonstrate how the GDC/PDC concept was intended to work before the 1971 final rule went into effect.

The examples of Indian Point 2 and Quad Cities were perhaps examples of what Hanauer meant when he described “fulfillment in principle.”

The Indian Point 2 (September 1966) application was built around the 27 criteria, and the staff testified that it satisfied all 27. Criterion 9 required that “at least two independent systems must be provided, preferably of different principles” for preventing core meltdown after an accident. IP2 proposed low-pressure safety injection pumps and residual heat removal pumps, running on systems that shared a common water supply. Based on their analysis, the regulators concluded “we do not believe that it is necessary for these systems to be of different principles in order to provide sufficient reliability.”

So, despite the criterion requiring separate independent systems preferably of different principles, the staff accepted the application with neither different principles nor independent water supplies.

Quad Cities (November 1966) relied on precedent. “The proposed reactors are substantially similar to the Dresden Units 2 and 3,” and the staff’s review was “essentially an extension of previous analyses performed on the Dresden and Millstone reactors.” Judgments against the 27 criteria were made where they applied.

Robinson Unit 2 (February 1967) provides another example of this process at work; the staff concluded in one paragraph that the proposed design “met the requirements” of the GDC published on November 22, 1965. It named several open items (“reactivity accidents, xenon stability, moderator reactivity coefficient effects, iodine removal, and emergency core cooling”), but was confident “adequate consideration has been given to the safety aspects of the unit to meet the requirements of the General Design Criteria.”

These examples show the criteria were in use as guidance and being applied by the staff with engineering judgment. The GDC provided the general principles, and the applicant’s PDC explained how they were met.

The Industry’s Divided Response, 1966-1970

Industry had conflicting opinions on the role and nature of the proposed GDC.

General Atomic provided comments on the 1965 criteria in February of 1966. It listed four primary concerns, one being “the fact that criteria which may seem desirable for water reactors may easily evolve into assumed precedents for other kinds.“

A rewrite of the 1965 criteria was submitted in February of 1966 by an industry consortium (Atomic Industrial Forum) representing such companies as GE, Bechtel, B&W, Westinghouse, and Yankee Atomic Electric. Their version characterized the GDC as defining or describing “the basic safety objectives to be met in the design of a nuclear power plant.” The proposed draft noted that some criteria in certain instances may be unnecessary or insufficient, and it acknowledged that “Many of the criteria can be met by alternative means depending on the design and location of the proposed reactor plant.”

In comments submitted separately, Black & Veatch thought the criteria should be published as a guide since they will be subject to revision from time to time. They were concerned that once written into the regulations, they would be set in stone and become too rigid for departure, unnecessarily limiting degrees of freedom: “We feel that if these criteria become a part of Part 50 Regulations that it would be very difficult to avoid direct literal interpretation even though the introduction does call them guidance for developing a specific plant design criteria.”

Combustion Engineering warned in its comments that criteria codified as mandatory will deter attempts to upgrade safety systems over time: “for either the criterion must be written so that it can be met by current design practice, in which case it has no upgrading effect, or it must be written to demand a higher standard of safety, in which case it cannot be met by current practice and the result can only be unpleasantness and frustration in the licensing activities of the near future.”

Others expressed similar concerns.

Wisconsin Electric did not want them codified into law because it would make them too hard to revise based on later experience and innovation. Commonwealth Edison thought that they should be published in the form of general performance guidelines.

In its October 1970 comments on the 1970 revision, the AIF protested “an unnecessary and unjustified escalation of licensing requirements.”

A minority of others, however, agreed with publishing them as minimum requirements, including Westinghouse, a reactor supplier.

Westinghouse, in its comments (September of 1967), characterized the criteria as “essentially minimum requirements.” They also asked that they be renamed to reflect their nature as being scoped to water reactors, arguing that other reactor types lack the operating experience, many of the criteria wouldn’t apply, and further study is required for them.

In short, the industry wanted certainty but feared escalation at the same time. As these things go, it got both.

Changing Attitudes, 1969-1971

By the end of 1968, 17 reactors had been built and operated with 9 still in continued operation. An Internal Study Group report in June of 1969 that included Hanauer as ACRS chairman assessed the current state of the licensing effort.

It noted that a “lack of a comprehensive set of regulatory safety criteria and industry codes and standards” was contributing to uncertainty and long safety evaluations. It highlighted the main problems mentioned by industry representatives as being “uncertainty and instability in regulatory requirements.” One of its recommendations was to publish concrete standards for backfits, which impose additional safety requirements after construction permits are issued. To eliminate this degree of uncertainty, they proposed moving from a case-by-case basis to rules requiring them “only if it finds that such action will provide substantial additional protection which is required for the public health and safety.”

The following month, Edson Case wrote to Hanauer, in a cover letter attached to the 1969 GDC revision that closed the gap between certainty and uncertainty, noted an inclusion of a clear statement that the revised criteria “Establish ‘minimum requirements’ for water-cooled reactors, whereas the published criteria were ‘guidance’ for all reactors.”

The 1969 revision included this framing in its introduction: “These General Design Criteria establish minimum requirements for the principal design criteria for water-cooled nuclear power units similar in design and location to units previously approved for construction by the Commission,” while also being “generally applicable to other types of nuclear power units and are intended to be used for guidance in establishing the principal design criteria for these units.”

With this narrowing of scope to water-cooled reactors, and the backfit rule now raising the bar for imposing additional, tougher requirements later, industry position softened. With the window on requirements closing, the regulatory staff seemed to recognize the need to reach for the stars because future requirement changes would be much harder to impose. The growth in the electrical criteria from 1965 to the final GDC 17 and 18 (above) show this window being used.

By 1971, with some of its comments incorporated and the 1970 backfit rule in place, despite the escalation in licensing requirements, the AIF was asking for “an effective rule.”

Details Move Into Guides

With the rule-making window closing, Harold Price moved in 1970 to begin issuing “Safety Guides,” which later became the Regulatory Guides. They would not be requirements, but they would be optional solutions that the licensees could implement if they so chose that would be acceptable to the Commission. “There is need for an expeditious means of providing additional guidance to applicants on the acceptability of proposed design features,” he wrote, since “Issuance of more specific AEC regulations can be a lengthy process because of the review time needed and the procedural requirements that must be satisfied.”

David Okrent, writing from his many years serving on the ACRS, confirmed this. “Since a process of promulgating new AEC regulations covering specific design criteria was expected to be slow and cumbersome, a more flexible approach was sought for the documentation of specific approaches acceptable to the Regulatory Staff (and the ACRS).” These optional guides flourished, with over a hundred guides being published by 1977.

Writing specifically about the Browns Ferry fire, Okrent stated that “a full-blown technical review of the adequacy of protection against fire ensued, and major, specific modifications were required, even on existing plants, without any change in the wording of Criterion 3.”

Separately, a 1967 proposal indicated parallel tracks being worked, including “supplementary criteria for the two main types of reactors, which are being developed in a joint effort with industry groups.” GE thanked the staff for joint opportunities to work on supplementary design criteria in 1967, and Westinghouse mentioned in its comments the supplementary criteria “now being prepared for pressurized water reactor systems.” These efforts eventually resulted in industry standards like ANSI N18.2 (PWR) and ANS-52.1 (BWR).

After the final GDC were published in 1971, the requirements continued to grow, but they found expression a layer down the stack, in regulatory guides and industry standards.

Before/After: How the Plants Used the GDC/PDC

The change in the nature of the two-tier relationship between the GDC as the floor and the PDC submitted by the applicants can be shown by examining how plant UFSARs as they read today (given that they are living documents) were written prior to 1971 and how they were written afterwards. After the final GDC were published, the role of the PDC faded.

Let’s first examine Nine Mile Point.

Section I.A opens with the principal design criteria philosophy:

The following paragraphs describing the principal design criteria are oriented toward the twenty-seven criteria issued by the United States Atomic Energy Commission (USAEC) on November 22, 1965. The twenty-seven criteria represented proposed "General Design Criteria for Nuclear Power Plant Construction Permits."

It then lists the 27 criteria, including electrical criterion 21: “Sufficient normal and emergency sources of electrical power must be provided to assure…”

Later, in its PDC section, it responds to 1965 Criterion 21: “Sufficient normal and standby auxiliary sources of electrical power are provided to assure…These features are discussed in Section IX.”

Section IX of the UFSAR (which became Chapter 8 in the standard UFSAR format) opens by stating “The Station electrical system is designed to provide adequate normal and emergency sources of electrical power for normal operation and for the prompt shutdown and continued maintenance of the Station in a safe condition under all credible circumstances.” It then provides a detailed description of the electrical system design basis and how the criterion is met.

The guidance-era GDC stated what needed to exist, and the PDC submitted by the applicant responded by saying that they do exist, and how.

Three Vintages in One UFSAR

Next, let’s examine Dresden 2 & 3, with construction permits issued in 1966. Here, three vintages of the GDC exist in a single UFSAR. It contains traces of the 1965 criteria, the proposed 70 criteria of 1967, and the final 1971 GDC.

Chapter 1 briefly mentions the PDC. Section 1.2.1 states “The principal criteria for design and construction of Units 2 and 3 are summarized below. Specific design criteria and design features are detailed in later sections.” It lists three general items, then gives criteria system by system. The electrical power requirements follow the Nine Mile Point pattern in Section 1.2.1.5: “Sufficient normal and standby auxiliary sources of electrical power are provided to attain…”

The Reactor Core criteria of 1.2.1.1 also track elements of the original 1965 criteria with backup shutdown independent of normal reactivity control (F–>Criterion 9), high-worth rod stuck out (E–>Criterion 8), and no power oscillations (B–>Criterion 5).

Section 3.1.1 notes that the GDC of 1967 were issued on a draft basis and were not yet adopted as regulatory requirements at the time of Dresden’s construction but “were used by the AEC to evaluate the original design of Dresden Station.” The review and evaluation of each of the 70 draft criteria documents relevant UFSAR section references demonstrating conformance, and many of them refer back to the PDC. For example, the review of Section 3.1.1.4.6, “Criterion 24 – Emergency Power for Protection Systems” cites UFSAR Section 1.2.1.5 of the PDC, along with Section 8.3.

Section 3.1.2 describes an audit of Unit 2 against the final GDC of 1971. While it concludes that Unit 2 “satisfies and is in compliance with the intent of the General Design Criteria,” it also notes that “Since much of this guidance was developed after Dresden was designed, it is inappropriate to infer that this conformance evaluation either creates commitments to or claims conformance to specific implementing guidance.”

Section 3.1.2 drops the PDC. It states that “The General Design Criteria, which are divided into six groups, are intended to establish minimum requirements for the design of nuclear power plants.” The final rule, however, states that “These General Design Criteria establish minimum requirement [sic] for the principal design criteria for water-cooled nuclear power plants…”

The point here is that Dresden’s audit against the 1971 GDC dropped the PDC tier from the UFSAR, referring to the GDC as minimum requirements for nuclear power plants instead of minimum requirements for the principal design criteria for water-cooled reactors. The role of the PDC was already diminished. The GDC were becoming the PDC.

Displaced: The GDC Are All That Matter

The final UFSAR to examine is Vogtle 1 & 2, a post-1971 reactor.

Section 1.2.12 is titled “Principal Design Criteria.” It opens by stating the plant is designed to comply with the intent of the General Design Criteria contained in Appendix A of 10 CFR 50. It points to section 3.1 for details of compliance with the GDC, then proceeds to list the plant’s PDC. But it’s just a list. The PDC are not evaluated against any standard demonstrating compliance; the GDC 17 evaluation in Section 3.1 responds with hardware, not a pointer back to Section 1.2.12.2.3.

For example, Section 1.2.12.2.3 contains the electrical power system criteria in just two sentences, and it follows the familiar pattern: “Sufficient normal and standby auxiliary sources of electrical power are provided to…”

Compare this to Section 3.1, which cites all of the final GDC verbatim and provides a detailed discussion of how the plant complies with each. The electrical discussion of GDC 17 describes the plant’s electrical topology, Class 1E and non-Class 1E power systems, the 230 kV switchyard, 13.8 kV underground circuits, 4.16 kV safety and non-safety buses, A and B trains, reserve auxiliary transformers, diesel generators, load sequencing upon power loss, and more. Chapter 8 then contains the full electrical section description per the standard UFSAR format.

Section 3.1.1 contains a single mention of the PDC: “The principal design criteria, design bases, codes, and standards applied to the facility are described in section 3.2.”

Despite the pointer, there is no mention of the PDC in Section 3.2. Further, there’s no evidence of any later section referring back to the PDC described in Section 1.2.12.

The point here is that the PDC exist in Vogtle’s licensing basis as a parallel list that is referenced by nothing and might as well be deleted without consequence. In fact, this is exactly what Hatch appears to have done. Unit 1’s UFSAR appears to follow the same layout as Peach Bottom, which lists its PDC in Section 1.5. In Hatch Unit 1, Section 1.5 is marked “deleted”. Hatch Unit 2 has no PDC section at all.

Compliance to the GDC is all that matters.

None of the three plants define “principal design criteria.” Across these three plants, the PDC move from being the criteria upon which the plant design is based to vestigial remnants of a licensing regime that’s faded away. When the applicant writes its design against the GDC instead of its own PDC, the minimum has become the standard.

PlantConstruction permit criteriaPDC in Ch. 1How the GDC are treated
Nine Mile Point 11965 (27)Plant PDC derived from the 27Assessed later; “not a commitment”
Dresden 2/31965; audited against 1967Restates 1965 criteria1967 “not … regulatory requirements”; 1971 paraphrased without the PDC tier
Vogtle 1/21971 (55)Parallel list, never referencedAnswered directly, criterion by criterion

The Light-Water-Cooled Path

Let’s return to the 1966 comments on the GDC issued by General Atomic, a non-water-reactor vendor. It issued multiple warnings:

  1. “It would be a great pity…if criteria developed under the influence of BWR and PWR experience to date were to become in any practical effect the rigid standards of the future.“
  2. “the risk that the agency staff members will as a practical matter adopt, as informal standards of their own, the tentative criteria and ideas which the Commission itself is not willing or ready to adopt in the regulations“

GA clearly saw the risk of the AEC issuing GDC based on prevailing technology leaders in the market.

Walker described in Containing the Atom (Chapter 2) how GE and Westinghouse established early market dominance with their light-water BWRs and PWRs due to their experience at Hanford and working with the US Navy. “By 1968, [GE and Westinghouse] had received 77 percent of the orders; Babcock and Wilcox and Combustion Engineering divided the remainder.”

A November 1965 criteria draft relied upon this dominance, which stated the draft criteria “reflect the predominating experience to date with water reactors.”

The 1965 Mitchell Panel had already recommended focusing on criteria for “those reactors which are being proposed for commercial installations in the greatest numbers” to allow “the staff and the ACRS to concentrate effort on new safety problems or on the safety problems of new types of reactors.”

But the Mitchell Panel also offered its own warning: “It is essential that any standards which are prepared do not slow progress in improved design, since this in itself could impair safety in the long run.“

We’ve already seen that Black & Veatch warned that codifying the GDC would make it “very difficult to avoid direct literal interpretation.”

And that Combustion Engineering warned of codifying current practice as the requirement.

Westinghouse asked in its comments on the draft criteria to narrow the scope to water-cooled reactors, and the 1969 revision did exactly that.

So, the GDC did not directly create light-water-reactor dominance. What they did do was codify its market lead and then set it as the floor. The minimum.

The Zero-Friction Path: Four Layers

The regulatory action that followed continuing lowering the cost for executing successive LWR builds and raising the cost for everyone else.

First Layer, the Rule: The 1971 final rule established the GDC in 10 CFR 50.34 as the “minimum requirements for the principal design criteria for water-cooled nuclear power plants similar in design and location to plants for which construction permits have previously been issued by the Commission.” They remain as “guidance” for the PDC for “other types” of nuclear plants.

Second Layer, Precedent: The Second Panel of 1967 mentioned that future reactor design features may be “virtually carbon copies” of previously licensed features, and the licensing boards should lean on those previous conclusions instead of re-litigating matters already covered. The Internal Study Group report suggested that “the present regulatory practice of conducting a single safety review for the identical design features of twin nuclear power plants at one site could be extended to cover identical design features of all plants of the same class.” They thought they could save review time if more applicants proposed duplicate designs. We’ve already seen above that the Quad Cities application review was considered an extension of previous analyses. A staff report in March of 1968 recommended packaging certain recommendations made by the Second Panel, including a statement of lineage in the application: “It is desirable for the applicant’s summary statement to include, as appropriate, a discussion of the evolution of the proposed reactor design, including associated engineered safety features, from the design of reactors which have previously been approved or built.”

In modern vernacular, the staff wanted to know if there was a “go-by” to which they should refer.

Third Layer, Supplementary Criteria: We’ve already seen that GE and Westinghouse were involved in separate efforts to develop supplementary criteria in cooperation with the AEC for BWRs and PWRs, which ultimately became ANS standards. These efforts were also mentioned in a 1967 amendment proposal.

Fourth Layer, Lock-In: The backfit rule was issued in 1970. The GDC were codified in 1971. Price and Okrent detailed how difficult it would be to issue more specific regulations from this point, noting that it would be “a lengthy process” and “cumbersome.” So, additional soft requirements, non-binding, kept coming through easier means, first issued in Safety Guides then as Regulatory Guides, that provided acceptable methods to implement certain regulatory requirements. Implementing alternative approaches not explicitly endorsed by the staff would require justification and individual review.

Each successive layer provided a subsidy for light-water reactors. Not in direct financial benefit, but in providing a deeper and wider licensing base that only light-water reactors could draw upon.

The Cost Imposed on Everyone Else

Now consider what would be required after 1971 to get a non-LWR through licensing.

The GDC were “guidance” for non-LWR applicants who had to write their own principal design criteria after 1971 and justify each departure. On paper, the GDC state that some requirements may not be applicable, and in some cases additional requirements may be needed: “For plants such as these, departures from the General Design Criteria must be identified and justified.”

Furthermore, they had no supplementary criteria jointly developed between the regulatory staff and industry, no type-specific guides issued by the AEC, no industry standards to draw upon, and barely any precedent available to cite.

One example demonstrating this path is Fort St. Vrain, a high-temperature gas-cooled reactor that received a construction permit in 1968. The AEC evaluated the PDC against the GDC, determined they met them, “and that any departures from these criteria have been identified and justified.” Along with Peach Bottom Unit 1, it was one of two HTGC reactors built in the United States (both by General Atomic). It operated for just 10 years, from 1969 to 1979. It had a greater thermal efficiency than LWRs and implemented a significant overhaul of multiple systems compared to Peach Bottom 1. It suffered numerous issues early on, and was shut down just as it was thought those issues were getting resolved.

The problem is that there were no succeeding HTGC reactors in line to absorb that operating experience. Fort St. Vrain was the last.

It wasn’t until April of 2018 that Regulatory Guide 1.232 was issued covering non-LWRs that the NRC clarified that exemptions do not need to be requested for departing from the GDC.

Forty-seven years after the GDC. Was it too late?

Warnings came from within the AEC and from without. General Atomic saw the handwriting on the wall as a non-LWR vendor, and Combustion honestly read the tea leaves even as a LWR vendor.

Here’s the scorecard:

Early commentPredictionOutcome
General Atomic, 1966Staff would “adopt, as informal standards of their own, the tentative criteria and ideas which the Commission itself is not willing or ready to adopt in the regulations”Safety Guides, 1970: “not regulatory requirements,” but adopting them meant assured acceptance
General Atomic, 1966Water-reactor criteria “may easily evolve into assumed precedents for other kinds”; “unequally rigorous standards of proof upon innovations”GDC as guidance for non-LWRs, with departures justified one by one; RG 1.232 came only in 2018
Mitchell Panel, 1965Standards could “slow progress in improved design, since this in itself could impair safety in the long run”Two HTGRs in 22 years; Part 53 in 2026
Black & Veatch, 1967Once in Part 50, “it would be very difficult to avoid direct literal interpretation”Plants answer the GDC directly (e.g., Vogtle)
Combustion Engineering, 1968Mandatory criteria either codify current practice or demand a higher standardThe “minimum requirements” became the design standard

None of this is to say that non-LWR didn’t receive federal money, because they did through the Power Demonstration Reactor Program (1955). Around 1970, the AEC was funding research into breeder reactors (which was suspended by President Ford in 1976 and terminated by President Carter in 1977).

Fort St. Vrain’s problems were real, but so were those on early LWRs. The difference is that market momentum helped overcome the problems, integrate the lessons learned, and encouraged the AEC to narrow its focus.

The rules didn’t banish non-LWRs from existence. Instead, they implemented competitive asymmetry that favored LWRs. Water reactors got a head start that compounded, and each compounding step raised the incremental cost of going a different route.

But a new hope appeared in 2026: Part 53.

Departure from the GDC: The Part 53 Rule of 2026

This brings us to the final step in this journey, the significance of the optional Part 53 rule that provides an alternative path to licensure issued in 2026: “Risk-Informed, Technology-Inclusive Regulatory Framework for Commercial Nuclear Plants.”

Neither “principal design criteria” nor “general design criteria” appear even once in the new rule.

In their place is a 4-step process:

  1. Establish plant-level safety criteria (Subpart B, “Technology-Inclusive Safety Requirements”)
    1. §53.210: limits for design-basis accidents, other licensing-basis events (§53.220), etc.
  2. Define safety functions: §53.230
    1. “The primary safety function is limiting the release of radioactive materials from the facility…”, and the functions “are required to satisfy the safety criteria defined in §§ 53.210 and 53.220 and must be fulfilled by the design features, human actions, and programmatic controls specified throughout this part.”
  3. Provide design features, human actions and programmatic controls: §53.400 (Subpart C, “Design and Analysis Requirements”)
    1. “Design features must be provided … such that, when combined with corresponding human actions and programmatic controls, the plant will satisfy the safety criteria defined in §§ 53.210 and 53.220.” (Also § 53.230)
  4. Define functional design criteria
    1. §53.410(a) and 420(a): required for each safety-related design feature or each design feature that is safety-related or safety-significant, shown to be met through “Analysis, appropriate test programs, prototype testing, operating experience, or a combination thereof…” [§53.440(a)(1)]

§53.440(a)(1) is the equivalent of the 10 CFR 50.34 design bases requirement. Instead of showing the relation of the design bases to the principal design criteria, the applicant must demonstrate that “each design feature required by § 53.400 meets the defined functional design criteria required by §§ 53.410 and 53.420.”

The NRC’S Quiet Concession

An important purpose of the Part 53 rule is to avoid “prescribing specific methods or processes…while eliminating traditional, prescriptive requirements, such as general design criteria and aircraft impact assessments.” The preamble of the final rule called special attention to two facts: the first is that the existing licensing frameworks “were primarily developed to address license requests concerning light water-cooled reactors;” the second, the fact that it’s “worth noting that licenses issued under parts 50 and 52 were largely based on deterministic analyses of the safety of the facility relying on the General Design Criteria.”

The NRC explicitly admitted the existing framework favored LWRs even though it began, and still contains pathways for, reactors of all kinds. By creating an entirely new rule, it’s implicitly admitting that this structure, from 1954 to 2026, imposed an asymmetric cost on non-LWRs, and now it may be trying to shift momentum.

The PDC in the NRC’S Own Words in 2026

In the comments on the preliminary rule, the NEI said the NRC “should discuss the definition of ‘functional design criteria’ for 10 CFR Part 53 in the context of principal design criteria.” The NEI noted further that “while the definition of principal design criteria focuses on the criteria being met by SSCs alone, principal design criteria may in fact be met by SSCs, human actions, programs, or a combination thereof.”

Two important items here.

First: as any astute reader of this article has realized, there is no formal definition of principal design criteria.

Second: the NRC explicitly rejected this idea.

The NRC explained that there are significant differences between the PDC of Parts 50 and 52 and the functional design criteria of Part 53. “Principal design criteria are a key part of a largely deterministic methodology and define specific design requirements and design rules against which the NRC reviews proposed reactor designs.”

The NRC essentially admitted that the PDC, the applicant’s own objectives, became the Commission’s rules for review. It also characterizes the PDC in terms that fit the GDC (“requirements and design rules” against which they rule reactor designs), which ties back into the displacement of the PDC by the GDC observed in UFSAR submittals.

A Return to the Original Structure

Another comment criticized the “case-by-case” evaluation that will emerge from 10 CFR 53.240’s requirements that each applicant identify their own licensing-basis events. The NRC disagreed, explaining that the new rules establish a technology-inclusive framework and “allow meaningful participation” in the process.

This is much closer to the 1954 and 1962 rules where the applicant proposes and the Commission evaluates than the framework that emerged after 1971. The NRC in a comment response also noted that functional design criteria more closely align with the definition of “design bases.”

General Atomic in 1966 had warned against codifying PWR and BWR experience that would become “the rigid standards of the future.” Part 53 is a response to the prediction 60 years later.

The Hope is Conditional: Resist the Pull

In other comments, the NEI asked that the rule be clarified to clearly state that the advanced reactor design criteria (ARDC) of RG 1.232 and the GDC be acceptable for generating ready-made versions of the new functional design criteria: “The commenter discussed that guidance should provide clarity that the GDC and ARDC in RG 1.232 are valid means of identifying functional design criteria under 10 CFR Part 53.”

That’s the gravity of the old framework pulling the new framework back towards reliance on precedent.

The NRC rejected this approach, stating that the criteria may be used as a starting point, but using the criteria “to inform the development of functional design criteria would be application-specific and reviewed by the NRC on a case-by-case basis.” It also noted in multiple instances that guidance remains forthcoming.

This is the same road that hardened the GDC to eventually displace the PDC and disadvantage non-LWRs. General Atomic warned about the staff adopting informal standards of their own.

So whether Part 53 works depends on how the NRC responds, whether it has internalized the hardening tendency laid out in this article and resists retreading the same old ground, or whether it gives into certain pressures.

This is especially worrisome given the pressures from within government and without alike on the NRC’s “staff shortage” created by issues with hiring, retention, and attrition. The AEC promulgated the GDC in part to alleviate the pressure associated with a tsunami of applications they felt would swamp them.

Conclusion

Murray Rothbard, writing in Power and Market from a manuscript he began in 1952, finished in 1959, and revised and published in 1970, wrote this about quality standards and safety codes. The mechanisms he described predicted the commercial nuclear power industry’s trajectory 1954-2026:

“Other quality standards in production have an even more injurious effect. They impose governmental definitions of products and require businesses to hew to the specifications laid down by these definitions…This is supposed to be a safeguard against ‘adulteration,’ but in fact it prohibits improvement. If the government defines a product in a certain way, it prohibits change…Yet it may take a long time, if not forever, to persuade the government bureaucracy to change the requirements. In the meantime, competition is injured, and technological improvements are blocked.” [pp. 51-52]

“Safety codes are another common type of quality standard. They prescribe the details of production and outlaw differences…On the other hand, administrative codes proliferate, and their general effect is to prevent major improvements in the building industry and thus to confer monopolistic privileges on existing builders, as contrasted with potentially innovating competitors.” [pp. 53-54]

It was almost as if the commenters from General Atomic and Combustion Engineering had read Rothbard’s work when they issued their warnings in their comments on the GDC. Non-LWR technology was stalled in the US, and the GDC as a “minimum” once codfied became the requirement. It has taken over 50 years to persuade the government bureaucracy to change the requirements, something that’s finally happened with the promulgation of Part 53.

The original framework established by the AEC required case-by-case review of the applicant’s principal design criteria. The AEC developed internal guidance for evaluating those criteria, and it released them for public comment in 1965 as guidance for applicants in developing their PDC in an attempt to streamline the application process.

Through almost six years of interaction with industry, these GDC hardened into minimum requirements for the PDC. After 1971, the GDC displaced the PDC almost completely in LWR applications. The minimum requirements became the de-facto requirements. Continued collaboration with industry further developed light-water-reactor supplemental criteria and regulatory guides that produced a deeper and deeper licensing base that compounded over time from which LWR vendors, and only LWR vendors, could draw upon to reduce application time and regulatory uncertainty.

Non-LWR vendors received no comparable regulatory groundwork. As a result, the US nuclear industry produced exactly two high-temperature gas-cooled reactors in 72 years of active licensing history (Peach Bottom 1 and Fort St. Vrain). A handful of other non-LWR types were built and operated as demonstration or test reactors (Fermi as a sodium-cooled fast-reactor, Hallam as a sodium-graphite reactor, Piqua as an organic-cooled and moderated reactor, and Carolinas-Virginia Tube Reactor as a pressurized heavy-water reactor). Since Fort St. Vrain shut down, no other non-LWR has operated commercially.

The NRC issued the Part 53 rule in 2026, and it offers a clean break that resets a half-century of deterministic licensing momentum that was built upon codified precedent and early dominance of LWRs. In its structure, it represents a return to the original form: applicants establish their own criteria, and the NRC evaluates them case-by-case. What’s new is the basis of those criteria, which are performance-based and risk-informed instead of prescriptive.

Against this background, non-LWR-types are being designed and moving through construction and operation, such as the sodium-cooled Natrium reactor by TerraPower and the molten salt reactor by Kairos.

The Kairos Hermes construction permit, a high-temperature, fluoride salt-cooled research reactor, was approved through Part 50 in 2020, as was the TerraPower Natrium sodium-cooled power reactor. Both followed RG 1.232 and submitted their own PDC.

Hermes adapted the GDC to its unique features, but it uses “deterministic evaluations for postulated events, the single failure criterion, and the maximum hypothetical accident of NUREG‑1537 to evaluate plant safety and classify SSCs” instead of the probabilistic approach of NEI 18-04.

Natrium, on the other hand, represented “the first use of a fully risk-informed, performance-based (RIPB) approach.” It also adapted the GDC, using it as a guide, and it identified and justified several exemptions.

Both reactors wrote their own PDC, applied RG 1.232, and followed the GDC numbering in their PDC topical reports following the non-LWR pathway through Part 50. PDC 17 and 18, for example, are electrical power.

Whether the NRC can resist the pull of converting the Part 53 rule into a streamlined licensing process that requires little engineering judgment in the face of public criticism about its low staffing levels remains an open question. Will the prophetic warnings of General Atomic and Combustion Engineering return to tighten down Part 53 and gradually squeeze out competing technology?

Will the reliance on precedent again reappear to neutralize Part 53 as an open path?

Part 53 removes the cost to a commercial non-LWR plant imposed by the exemption process of Part 50, a framework that has been largely tailored to fit water-cooled PWRs and BWRs. But both Hermes and Natrium are now precedents that can be cited as having passed through Part 50. Natrium used the same framework upon which Part 53 is based, but it wouldn’t have needed the exemptions if Part 53 were open to it. It will likely need more for its operating license. The first applicant through Part 53 will be bearing greater risk than the applicants that come after him.

And, perhaps last but not least, there still remains, to this day, no definition of “principal design criteria” to be found in 10 CFR Chapter I. Yet the structure built around the undefined term (applicant-written criteria supported by a Commission base of “general design criteria,” with each departure justified) was copied into the rules for geologic repositories (Part 60) and spent fuel storage (Part 72). Part 53 is the first licensing framework to leave it behind.

Since over 60 years have passed since the word’s first appearance in the proposed 1966 rule, I doubt at this point one will ever appear.