10 CFR 50.59 – A history of the rule’s development
Prior to 1962, the 50.59 process for modifying a nuclear plant without requiring prior Commission approval did not exist. There was no UFSAR. There…
The Nuclear Electrical Engineer
Here you can find design tips on technical skills like cable and breaker sizing, short-circuit evaluations and more, PLUS deep-dive analysis of nuclear-specific topics like design basis, Tech Specs, UFSARs, and safety-related SSCs — built from primary source documents.
Prior to 1962, the 50.59 process for modifying a nuclear plant without requiring prior Commission approval did not exist. There was no UFSAR. There…
It’s given as guidance in NEI 96-07 without a basis, and 10% is not mentioned in the regulations at all. But the basis isn’t…
This may be helpful to you when you take it. Half of those who took it with me failed on their first attempt…
There are several color-coding schemes for control cables. Get quick links to them here…
Next-generation nuclear plants are more expensive to build in the United States than elsewhere in the world, like in China. A group of researchers…
Iowa’s only nuclear plant is said to stimulate $255 million in economic activity in the state, and about half a billion nationally…
Flow meters are frequently used and installed in nuclear plants. But there are numerous factors to consider when selecting the correct one for the…
The nuclear power industry could be facing the loss of four more units and 4,048 megawatts of power…